Asbestos assessment, daily airborne fibre monitoring and staged clearance support during remediation works within a live road corridor.
.png)
BBN Consulting provided asbestos assessment, monitoring and clearance support for the Mona Vale Road East Upgrade after asbestos was identified on the ground surface and within soil near the existing road and proposed widening works.
The scope began with site inspections and assessments to define the extent of impacted material and guide removal requirements. During the three month remediation program, BBN provided daily airborne fibre monitoring and supervision, with clearance inspections issued progressively as each section was completed.
01. PROJECT CONSIDERATIONS
» Asbestos identified on the ground surface and within soil
» Impacted material located beside existing road and widening works
» Remediation required within a busy live road corridor
» Daily monitoring and supervision required during removal works
» Staged clearance inspections needed as sections were completed
02. VALUE DELIVERED
» Defined asbestos impacts across affected work areas
» Provided clear recommendations to guide removal works
» Supported safe remediation through daily monitoring and supervision
» Issued staged clearances as sections were completed
» Helped works progress safely within a major infrastructure project